By Buddy Nevins, BrowardBeat.com, for SouthFloridaReporter.com, Aug 29, 2015 – Parkland’s City Commissioners Friday were expected to accept a year’s delay in the construction of classrooms caused by School Board staff mistakes.

The School Board’s staff has been unable to get a mere eight classrooms built even though Parkland is paying for them.

To make matters worse,  the schools staff now says they were wrong in estimating the cost of the classrooms. They can only build a maximum of seven (or six), not eight, portables for the $2 million Parkland is paying.

The Board promised in a written contract to have the classrooms open by the start of the school year. The School Board staff couldn’t get that done

Faith Based Events
[vc_cta_button title=”CONTINUE READING” target=”_blank” color=”btn-info” icon=”none” size=”btn-large” position=”cta_align_bottom” css_animation=”appear” href=”http://www.browardbeat.com/school-supt-runcies-latest-spin-about-construction-delays/”]

Disclaimer

Artificial Intelligence Disclosure & Legal Disclaimer

AI Content Policy.

To provide our readers with timely and comprehensive coverage, South Florida Reporter uses artificial intelligence (AI) to assist in producing certain articles and visual content.

Articles: AI may be used to assist in research, structural drafting, or data analysis. All AI-assisted text is reviewed and edited by our team to ensure accuracy and adherence to our editorial standards.

Images: Any imagery generated or significantly altered by AI is clearly marked with a disclaimer or watermark to distinguish it from traditional photography or editorial illustrations.

General Disclaimer

The information contained in South Florida Reporter is for general information purposes only.

South Florida Reporter assumes no responsibility for errors or omissions in the contents of the Service. In no event shall South Florida Reporter be liable for any special, direct, indirect, consequential, or incidental damages or any damages whatsoever, whether in an action of contract, negligence or other tort, arising out of or in connection with the use of the Service or the contents of the Service.

The Company reserves the right to make additions, deletions, or modifications to the contents of the Service at any time without prior notice. The Company does not warrant that the Service is free of viruses or other harmful components.